Carefully differentiate the following by describing and explaining the construction of each part.

A. Main/Primary/perimeter dike

B. Secondary Dike

C. Tertiary Dike



B Think Wisely Carefully Differentiate The Following By Describing And Explaining The Construction Of Each PartA MainPrimaryperimeter DikeB Secondary DikeC Tert class=

Sagot :

Answer:

A.

perimeter dikes is to retain water for use in the fish farming operation

B.

secondary dike is smaller than the main dike. It is constructed when the whole area is already enclosed by the main dike.

C.

Tertiary dikes are partition dikes that separate the ponds and should be able to contain the desired water levels in the ponds

Explanation: