A front end loader needed to apply 200 N of force to lift a rock. A total of 275 J of work was done. How high was the rock lifted?

Sagot :

Answer:

 1.375 m

Explanation:

      d = W/F

         = 275 N·m / 200 N    (cancel same units)

        = 1.375 m

Note:

  1 J = N·m