Sagot :
1.) 2 Days
Solution:
The farmers can do it in 2 days because the 3 farmers can do it in 4 days.The lower the farmers are higher the days.The many the farmers are lower the days.
2.) 1 Day
Solution:
The 5 sewers can do 200 children's dresses in 8 days.In 10 sewers they can finish 200 childres's dresses in a day.
#CARRY ON LEARNING
Question
3. If 3 farmers can plow a field in 4 days, how long will 6 farmers do it?
4. Five sewers can finish 200 children's dresses in 8 days. How many days will take 10 sewers to finish the same number of children's dresses?
with solution pls
Answer
3. 8 Days
4. 18 Days
Solution
3. 4 + 4 = 8 Days
4. 10 + 8 = 18 Days
#CarryOnLearning
#LetsStudy