if 8 boys can finished their project in 12 days how many boys will be required to finished their project in 16 days?

solutions:



nasa pic po ung example.

pls paki sagutan ung maayos po at tama

pag mali report ko​


If 8 Boys Can Finished Their Project In 12 Days How Many Boys Will Be Required To Finished Their Project In 16 Dayssolutionsnasa Pic Po Ung Examplepls Paki Sagu class=

Sagot :

Answer:

6 boys

Step-by-step explanation

12/16 = n/8

12x8 = 16xN

96 = 16N

96/16 = 16N/16

6 = N

Checking: 12 x 8 = 96

16 x 6 = 96