Answer:
Three point estimating is a technique which utilizes an optimistic and pessimistic estimate to determine the ideal estimate value for a project task. ... It allows known risks to be quantified and built in to the project budget.
Explanation:
3-Points is a technique that involves people that are professional in the task we are estimating by this technique. ... The third estimate is the optimistic (O) estimate which is the amount of work the task might take if the positive risks they identified do occur.
----------------------------------------------------------