Sagot :
Answer:
PERT deals with unpredictable activities, but CPM deals with predictable activities. PERT is used where the nature of the job is non-repetitive. In contrast to, CPM involves the job of repetitive nature. ... PERT is best for research and development projects, but CPM is for non-research projects like construction projects.
Explanation:
;-)
Answer:
PERT deals with unpredictable activities, but CPM deals with predictable activities. PERT is used where the nature of the job is non-repetitive. In contrast to, CPM involves the job of repetitive nature. ... PERT is best for research and development projects, but CPM is for non-research projects like construction projects.
Ang iyong aktibong pakikilahok ay mahalaga sa amin. Magpatuloy sa pagtatanong at pagbahagi ng iyong nalalaman. Sama-sama tayong lumikha ng isang masiglang komunidad ng pagkatuto. Salamat sa pagpili sa IDNStudy.com. Umaasa kami na makita ka ulit para sa mas maraming solusyon.