48 men can do a piece of work in 24 days while 36 men complete the same work in 32 days the fewer the worker the longer to finish the job explain your answer​

Sagot :

Answer:

48men completed the work in 24 days,

Amount of total work completed = 48*24=1152 units.

If the total work is completed by 36 men they will be taking 1152/36 men = 32 days.

In all time-work related problems, more workers mean that total work will be completed in less time, also few workers mean it takes more time to complete the Same amount of work.

Work = workers * Time taken

Hence, Workers and time taken are inversely proportional to each other. If one increases other decreases.