Tuklasin kung paano ka matutulungan ng IDNStudy.com na makuha ang mga sagot na kailangan mo. Sumali sa aming platform upang makatanggap ng mabilis at eksaktong tugon mula sa mga propesyonal sa iba't ibang larangan.

Ann and Mary together can do a piece of work in 4 days. Ann and Naty can do the work in 6 days. Mary and Naty can do it in 5 days.how long would it take each to do the work ?

Sagot :

let 'x' be the rate of Ann to finish the job
    'y' be the rate of Mary
    'z' be the rate of Naty
x(4) + y(4) = 1
 4x + 4y = 1    ----equation 1

x(6) + z(6) = 1
 6x + 6z = 1   ----equation 2

y(5) + z(5) = 1
 5y + 5z = 1   ----equation 3

multiply equation 1 with 6 and equation 2 with 4
4x + 4y = 1
24x + 24y = 6   -----equation 1'
6x + 6z = 1
24x + 24z = 4  -----equation 2'

subtract equation 2' from equation 1'
24y - 24z = 2
 dividing the whole equation by 2
 12y - 12z = 1  ------equation 4
multiply equation 3 with 12 and equation 4 with 5
5y + 5z = 1
60y + 60z = 12  ----equation 3'
12y - 12z = 1
60y - 60z = 5    -----equation 4'
add equation 4' and equation 3'
120y = 17
y = 17/120
substitute the value of y to equations 1 and 3
4x + 4y = 1
4x + 4(17/120) = 1
4x = 1 - 68/120
4x = 13/30
x = 13/120
5y + 5z = 1
5(17/120) + 5z = 1
5z = 1 - 85/120
5z = 7/24
z = 7/120
to get the time for each to finish the job alone, get the reciprocal of the rates.
y = 17/120
t(y) = 120/17 days
t(y) = 7.06 days
x = 13/120
t(x) = 120/13 days
t(x) = 9.23 days
z = 7/120
t(z) = 120/7 days
t(z) = 17.14 days
[tex]A+M=4 \\ A+N=6 \\ M+N=5 \\ ======= \\\\ 2A+2M+2N=4+6+5 \\\\ 2(A+M+N)=15 \ |:2 \\\\ A+M+N=7.5\\ A+M=4 \\\\ =>N=7.5-4 \ \ \to\boxed{N=3.5 } \ (3 \ days \ and \ a \ half \ for \ Naty) \\\\\\ A+M+N=7.5 \\ A+N=6 \\ \\ => M=7.5-6 \ \ \to\boxed{M=1.5} \ (1 \ day \ and \ a \half \ for \ Mary) \\\\\\ A+M+N=7.5 \\ M+N=5 \\ \\ => A=7.5-5 \ \ \to\boxed{A=2.5} \ (2 \ days \ and \ a \ half \ for \ Ann)[/tex]