IDNStudy.com, ang perpektong platform para sa mabilis at eksaktong mga sagot. Tuklasin ang malawak na hanay ng mga paksa at makahanap ng maaasahang sagot mula sa mga bihasang miyembro ng aming komunidad.

Remember, Labor cost = Daily labor requirements X Duration X Cost per day = 3 laborers X5 days X 300 = Php 4,500 12,000. 00 10,500. 00 7,500. 00 15,000. 00 9,000. 00 10,000. 00 Activities Nature of Daily labor Duration Appointment requirements (Days) (8 hours/day) Daily 7 laborers 5 Labor cost (P300/day) ? 10 laborers 5 ? 1. Marking the dikes 2. Construction of dikes 3. Installations of gates 4. Construction of gaies 5. Finishing touches Contract labor Contract labor Daily 6 laborers 5 2 5 laborers 5 2 Daily 8 5 2.