Makakuha ng eksaktong mga sagot sa iyong mga tanong sa IDNStudy.com. Sumali sa aming platform ng tanong at sagot upang makakuha ng eksaktong tugon sa lahat ng iyong mahahalagang tanong.

Remember, Labor cost = Daily labor requirements X Duration X Cost per day = 3 laborers X5 days X 300 = Php 4,500 12,000. 00 10,500. 00 7,500. 00 15,000. 00 9,000. 00 10,000. 00 Activities Nature of Daily labor Duration Appointment requirements (Days) (8 hours/day) Daily 7 laborers 5 Labor cost (P300/day) ? 10 laborers 5 ? 1. Marking the dikes 2. Construction of dikes 3. Installations of gates 4. Construction of gaies 5. Finishing touches Contract labor Contract labor Daily 6 laborers 5 2 5 laborers 5 2 Daily 8 5 2.